Phase 1 Construction Update

The Contractor switched traffic yesterday on Ingersoll Avenue and will now finish work on the south side of the road.  Work is expected to take approximately one month.  During this time, two-way, head to head traffic will be maintained on the north side of Ingersoll Avenue.  Sidewalks will remain open and business access will be maintained during construction; however, there will be no street parking.

The Contractor will also start installing storm sewer pipe next week in the parking area behind businesses, north of Ingersoll Avenue, between 28th Street and 29th Street.  Access to business and parking will be maintained and areas with open trenches will be fenced off during non-working hours to maintain safety.  Work will start at 28th Street and progress westerly to 29th Street and is on schedule to be completed by the end of November. 

If you have additional questions or concerns, please contact Craig Bouska at (515) 283-4580.