Phase 1 Construction Update

Construction of the Near West Side Sewer Separation Phase 1 Project on Ingersoll Avenue will be starting on Tuesday morning, September 5, 2017.  The Contractor will be closing the north half of Ingersoll Avenue from 23rd Street to 28th Street.  Two-way, head to head traffic will be maintained on the south side of Ingersoll Avenue.  Work is anticipated to be completed in November and includes installation of new storm sewer pipe and street reconstruction. Sidewalks will remain open and business access will be maintained during construction; however, there will be no on-street parking.  Upon completion of the north half of Ingersoll Avenue, the Contractor will complete storm sewer connections to the south side of Ingersoll Avenue with street patching.

If you have additional questions or concerns, please contact Craig Bouska at (515) 283-4580.”